Payment & works schedule guide
Use this as a reference when reviewing a builder's payment schedule. The right schedule protects both sides — you pay only for work that's been done and signed off, and your builder gets paid promptly for genuine progress.
Homeowner protection
Typical UK deposit is 10–15% of contract value, released on signing to cover initial materials and mobilisation.
On smaller trade jobs (single bathroom, boiler, rewire) up to 20–25% is acceptable where the trade is buying fittings up front — but ask to see supplier invoices.
Never pay more than 25% before any work has started or materials have arrived on site.
Hold back 5% retention against snagging until all defects on your snag list are cleared.
On larger projects (£100k+) it's normal to hold half the retention for a defects period of 3–12 months after practical completion, to catch settlement cracks and faulty fittings.
Use our Snagging Inspector before releasing the final stage payment.
- Asked for cash-only payments or transfers to a personal account.
- Deposit over 25% before any materials are on site.
- No written contract or no agreed payment schedule.
- No proof of public liability insurance (£2m+).
- No Companies House number for a limited company builder.
- Pressure to pay the final stage before snagging is signed off.
- Refusal to provide a VAT invoice when registered.
- All snags walked, listed in writing, and agreed.
- Building control sign-off issued (where required).
- Gas Safe and Part P certificates received.
- FENSA / CERTASS certificates for windows.
- Boiler commissioning certificate and benchmark filled in.
- Manuals and guarantees collected (boiler, kitchen, appliances).
- Retention released only after defects period (commonly 5% for 3–12 months).
Recommended payment schedules
Standard extension or new-build
6 stagesSingle/double-storey extensions, garden rooms, small new-builds. Contract values £25k+.
Loft conversion
5 stagesDormer, hip-to-gable, mansard, Velux conversions. Contract values £30k–£80k.
Kitchen or bathroom refurb
4 stagesSingle-room refurbs where the builder isn't buying the units. Contract values £8k–£25k.
Roofing & external works
3 stagesFull re-roof, flat roof replacement, rendering, driveways. Contract values £5k–£20k.
Works milestones — what good looks like
Pre-start
Contract, payment schedule and programme of works signed by both parties. Building control / planning approvals in place. Builder's insurance certificates supplied.
- • No written contract
- • Deposit over 25% before any work
- • Builder won't provide insurance documents
Site set-up & strip-out
Welfare, skips, scaffolding, dust protection in place. Existing structure protected.
- • Site left unsecured at end of day
- • No dust sheets / floor protection inside
Structural works
Foundations, steels, load-bearing alterations. Building Control inspections signed off before backfilling or hiding the work.
- • Foundations covered before BC inspection
- • Steels installed without engineer's sign-off
Watertight / shell complete
Roof on, openings closed, internal areas dry. Natural payment stage.
- • Asked to pay before the roof is fully closed in
- • Visible water ingress
First fix M&E
Plumbing, electrical, heating in walls and floors. Take photos of every wall before plastering.
- • No photos of routes
- • Electrician/plumber not NICEIC / Gas Safe registered
Plastering & ceilings
Boards up, skimmed, dried out before paint or second fix.
- • Second fix happening on damp plaster
- • Cracking at junctions not addressed
Second fix & fit-out
Doors, skirting, sockets, switches, sanitaryware, kitchen units, flooring.
- • Damaged finishes accepted without note
- • Appliances stored on bare plaster floors
Snagging
Walk the job with the builder. List every defect, agree a fix date. Retain ≥5% until snags are cleared.
- • Builder pressing for final payment with open snags
- • No retention held back
Handover & documentation
Building Control completion certificate, electrical (EICR / minor works), Gas Safe, FENSA, product warranties, workmanship guarantee.
- • No completion certificate
- • Verbal guarantees only — get them in writing
When your builder sends a schedule
You're not obliged to accept it as-is. You can edit any stage and send your version back for the builder to accept or reject. Both sides have to agree before any work starts.
