Pre-construction (typical 10–16 weeks)
Architect or designer: 3–5 weeks for measured survey and concept drawings. Planning or PD route: 4–8 weeks. Structural engineer: 2–3 weeks. Building Control plans: 2 weeks. Builder tendering and contract: 2–4 weeks. This phase is where most overruns originate — start it before you commit to a builder start date.
On-site construction phases
Single-storey rear extension (25–35 m²): 10–14 weeks. Loft conversion (dormer): 8–12 weeks. Kitchen refit: 4–6 weeks. Full bathroom: 2–3 weeks. Whole-house refurb: 4–7 months. Add 2 weeks for snagging and final account.
Local factors that move the schedule in Lancaster
Party-wall agreements (terraced and semi-detached homes in Lancaster): allow 6–8 weeks. Material lead times for bi-fold doors and bespoke joinery: 8–12 weeks. Building Control inspections in Lancashire: book at least 3 working days ahead. Builder availability for autumn starts is tight — secure dates 4+ months ahead.
What "on time" actually means
Industry data: only ~30% of UK domestic projects finish on the original date. A realistic plan adds 15–20% buffer to the builder's headline duration. Lock dates with a Payment Schedule tied to stages, not weeks — that protects you when the timeline slips.
